Port Adelaide Office Accommodation Progress Update

The chillers have been lifted and installed on the upper plant deck. 

Steady progress was made in the lead up to Christmas at Port Adelaide on Levels 3, 4 and 5. 2017 finished on a high with the lifting and installation of the Smardt chillers to the upper plant deck (Level 6).

Early 2018 will see the AHU’s, boilers, buffer tank, expansion equipment and pumps installed. This will bring the plantroom into focus allowing mechanical plumbing, electrical and duct installation to commence.

With a big push over the next 6 to 8 weeks the site team is aiming to break the project open ready for our gun commissioning gurus to get involved…..watch this space!